EXAMPLE 1
1. On December 1, 20X4, Compassionate
Inc. began construction of homes for those families that were hit by the
tsunami disaster and were homeless. The construction is expected to take 3.5
years. It is being financed by issuance of bonds for GHS7 million at 12% per
annum. The bonds were issued at the beginning of the construction. The bonds
carry a 1.5% issuance cost. The project is also financed by issuance of share
capital with a 14% cost of capital. Compassionate Inc. has opted under IAS 23
to capitalize borrowing costs. Required Compute the borrowing costs that need
to be capitalized under IAS 23.
EXAMPLE 2
On 1
January 20X6 Stremans Co borrowed $1.5m to finance the production of two
assets, both of which were expected to take a year to build. Work started
during 20X6. The loan facility was drawn down and incurred on 1 January 20X6,
and was utilised as follows, with the remaining funds invested temporarily.
EXAMPLE 3
Acruni Co
had the following loans in place at the beginning and end of 20X6.
1
January
31 December
20X6
20X6
$m
$m
10% Bank
loan repayable 20X8 120
120
9.5% Bank
loan repayable 20X9 80
80
8.9%
debenture repayable 20X7 – 150
The 8.9%
debenture was issued to fund the construction of a qualifying asset (a piece of
mining equipment), construction of which began on 1 July 20X6.
On 1
January 20X6, Acruni Co began construction of a qualifying asset, a piece of
machinery for a hydroelectric plant, using existing borrowings. Expenditure
drawn down for the construction was: $30m on 1 January 20X6, $20m on 1 October
20X6.
Required
Calculate
the borrowing costs that can be capitalized.
Suspension of Capitalization of Borrowing Cost:
If during the period of
construction, the activities necessary to complete the asset are interrupted or
suspended due to particular reasons, the borrowing cost of such period will be
accounted for as follows:
If the period of interruption
is material, the borrowing cost of such period will not be capitalized and
will be charged to statement of profit and loss as an expense.
If the period of interruption
is immaterial or temporary such as (Material shortage or labor
strikes), then entity may continue to capitalize the borrowing cost during such
period.
Cessation of Capitalization:
The capitalization of the borrowing
cost will cease, when activities necessary to complete the asset are
finished i.e. the completion of the physical structure of the qualifying asset,
although some administrative or decorative work may still continue.
If a qualifying asset
contains different component parts such as (Industrial plant which
has several processes) and the entity will complete the construction of such
qualifying asset by constructing each part or component on individual
basis in a sequence, where each part or component can be used individually
while the construction work is in progress on other parts or components, the
capitalization of the borrowing cost will cease when activities necessary to
complete that part for its intended use or sale has been finished.
Thanks for the blog loaded with so many information. Stopping by your blog helped me to get what I was looking for. chartered building surveyor london
ReplyDeleteHopefully, most people that become Doctors, want to be Doctors. If someone is going to go digging around in my belly, I want them to enjoy what they're doing and not wish they were out leading a group of fisherman on a flounder trip. Secretarial Services
ReplyDelete